Commissioning
Test Sheet
Sepam™ Series 80
Project: Type of Sepam™
Switchboard: Serial Number
Cubicle: Software Version
V
Overall Checks
Check v when the check is made and is conclusive
Type of Check
Preliminary general examination, prior to energizing
v
Energizing
v
Parameter and protection settings
v
Logic input connections
v
Logic output connections
v
Validation of the complete protection chain
v
Validation of the adapted functions (via the logic equation editor or via Logipam)
v
Analog output connection to the MSA141 module
v
Temperature sensor input connections to the MET148-2 module
v
Voltage input connections to the MCS025 module
v
Checing Phase Current and Voltage Inputs
Check v when the check is made and is conclusive
Type of Check Test Performed Result Display
Phase current and phase
voltage input connections
Secondary injection of CT
rated current into
,
1A or 5A
Rated primary current of CTs
connected to
Ia =....................
v
Ib =....................
v
Ic =....................
v
Secondary injection of phase
voltage (the value to inject
depends on the test being
performed)
VT rated primary phase-to-neutral
voltage V
LLp
/3
Va = ..................
v
Vb = ..................
v
Vc =...................
v
Phase displacement ϕ(V, I) ≅ 0° ϕa =...................
v
ϕb =...................
v
ϕc =...................
v
Phase current input
connections for differential
applications
Secondary injection of CT
rated current into
/,
1A or 5A
(1A if secondary ratings are
different)
Primary In (or In/5) of CTs
connected to
(depending on secondary ratings)
Ia =....................
v
Ib =....................
v
Ic =....................
v
Primary I’n (or I’n/5) of CTs
connected to
(depending on secondary ratings)
I’a = ...................
v
I’b = ...................
v
I’c = ...................
v
Phase displacement θ(I, I’) ≅ 0° θ(Ia, I’a) =..........
v
θ(Ib, I’b) =..........
v
θ(Ic, I’c) = ..........
v
Tests performed on: .....................................................................
By: ...................................................................................................
Signatures
Comments:
......................................................................................................................................................................................................
...............................................................................................................................................................................................................................
...............................................................................................................................................................................................................................